Hi,

yes, old I know, but I still use DA2000 (whilst evaluating DAWS, which is excellent).

However, I have a problem with DA2000 in that if I set a multilist schedule, say to run at 1800, 1810 and 1820 only the 1800 works and then the computer seems to ignore the others, i.e.e the schedule works once.

OS is Windows98.

Anyone any suggestions (polite only please :) )

Thanks,
Simon

Simon Keeling

Posted: Wed Jul 07, 2004 6:47 pm
by Wally Mayo
Might need more info, but let me take a stab.

Sometimes the scheduler "unchecks" the box (enable scheduler) at the end of a script. I have found that putting "timer on" at the end of all scripts cures this problem.

(This applies to DA 1.0a)